OAO «MRSK of Ural» continues realization of large-scale investment project – building of substation 220/10 kv «Ann», located in Sukholozhskom city district of the Sverdlovsk area. Power engineering specialists of the East electric networks of the Sverdlovsk branch of OAO «MRSK of Ural» began editing of basic energooborudovaniya  to new substation. So, already foundations geared-up under the equipment of new energoob’ekta, purchased and set power
transformers 220 kv, it is mounted nine from twenty four disconnectors, setting of metallokonstrukciy of portals of the opened distributive devices is executed, editing of navesnogo equipment is conducted on power transformers.For building new
to the air-track of electricity transmission by the class of tension 220 kv, which will carry out the feed of substation 220/10 kv «Ann», power engineering specialists of OAO «MRSK of Ural» began clearing of route and assembling of metallic supports, executed editing of transition of VL 220 kv through VL 500 kv. 
So, in the near time, on the wood lots of Bogdanovicheskogo and Sukholozhskogo of city districts of the Sverdlovsk area under building of air-track 220 kv specialists of the East electric networks of OAO «MRSK of Ural» will prepare a 23 km of route, just the same extent
will have this energoob’ekt., that substation 220/10 kv «Ann» by the general set power 80 MVA intended for the power supply of the built fifth technological line  OAO «Sukholozhskcement», one of the largest producers of cement on
Ural. On building of energoob’ekta OAO «MRSK of Ural» will send 1, 26 milliard of roubles.