OAO «Karelia energosbytovaya company» sent to managing OAO «Segezhskiy CBK», to the public prosecutor of district and leader of Administration Segezhskogo district letter in which advises about the forced limitation of the mode of energy consumption of enterprise. In connection with that OAO «Segezhskiy CBK» in 2009 repeatedly violated the terms of payment of electric energy, on being in May, 18, 2009, a debt appeared before OAO «KESK» in size of 177 million 860 rub. sent notification in an address a debtor
about the necessity of debt and introduction of independent limitation of consumption of electric power liquidation to the level of technological armour. None of requirements of power engineering specialists to a full degree executed guidance of enterprise was not, was therefore accepted
decision about the forced limitation of the mode of energy consumption of debtor by disconnecting of one of two LEP 110 kv, and the proper request is given in a network company.At the same time power engineering specialists are disturbed by that in case of occurring of loadings of spades, remaining
in-process a line will not be able to function in full, that will result in disconnecting of automation of relay defence. And, as a result, to the complete disconnecting of city and combine. In this situation, considers «Karelia energosbytovaya company», it is necessary to unite
efforts of all interested parties and to take measures to implementation of the obligations a debtor under payment of electric power or independent limitation of energy consumption and bringing him over to solvent demand.