Labinskie electric networks are a branch «South MRSK» – «Kuban’energo» – conducts complex repair of substation 35/10 kv «High», located in Kurganinskom district. The specialists of service of substations of Labinskikh of electric networks already produced major repairs of oily switches 10 kv, oily switch 35 kv, disconnectors 35 kv and cells of Krun-10 kv on substation «High». To date permanent repair is produced
power transformer by power 1,6 MVA and transformer of own needs 110/10 kv. The power engineering specialists of remontno-stroitel’nogo area complete work on repair of a build part of substation: repair of maslopriemnikov and foundation under energooborudovanie.
repair of PS 35/10 kv «High» will allow considerably to promote quality and reliability of energy supply of users of settlement High Kurganinskogo of district.