Kurskie power engineering specialists of OAO «MRSK of Center» began complex major repairs of substation equipment. Works began one of the first on substation 110/35/10 kv «Rybinskie Budy». It is key substation of production separation «South electric networks». Reliability and quality of energy supply of users of south territories of the Kurskoy area depends On its work.On a chart repair of substation will be completed by the end of April. That not
to interrupt the power supply of users, by contract organization is the mechanized column 12 — executes works stage-by-stage.Complex repair of substations gives the economy of financial and labour expenses to the branch. The object repaired by such method will not demand
capital investments at least six years. In 2008 in «Kurskenergo» 45 substations were repaired, in current it is planned to renew 39 substations 35-110 kv. On these aims poryadka 24 million roubles are foreseen.