Power supply in Nazarovo and Nazarovskom district, broken by a hurricane, it will be fully recovered to the end of day of May, 19. We will remind that a hurricane rushed past above Nazarovo in the day-time on May, 18. Gustings exceeded a 28 m/p. Falling of trees and large branches, bringing down of roofs of houses on the line of electricity transmission became reason of disconnecting from the power supply of part of habitants of city Nazarovo and near-by settlements.In order that operatively to recover a power supply,
power engineering specialists work round-the-clock. The consequences of hurricane remove 10 operativno-remontnykh brigades of the Western electric networks «Krasnoyarskenergo». Power engineering specialists clear the routes of lines of electricity transmission from laying low trees, works conduct on lines.As a result,
greater part of users of Nazarovo and Nazarovskogo of district was connected to the power supply to 22 hours of May, 18. Fully a power supply in a district will be recovered to the end of day of May, 19.