Director general MRSK North-west Alexander Kukhmay on the conference of workinggroups of Council of co-ordination of development of TEK at a plenipotentiary in SZFO presented a lecture «About balances of the work of first-year of the incorporated elektrosetevoy company MRSK North-west». Speaking about principles works of the incorporated company, which work of OAO is built on «MRSK of North-west», a director general selected two basic aspects is the account of interests of regions and regional principle of division of expenses. «Following these principles,
we provide balance of interests of territories which are included in the area of our responsibility and network organization,
the incorporated network company to a full degree provides single responsibility on all territory, designing and managing the financial state of branches of MRSK of North-west, as independent enterprises. For a year work in status of the incorporated company
MRSK of North-west formed long-term investment strategy, which plugs in itself the plans of development of territories, charts of development of elektrosetevykh objects, plans of technical rearmament and reconstruction, taking into account a physical and moral wear
network complex. The volume of capital investments of MRSK of North-west in 2008 exceeded 4 milliards of rub, that on a 881,6 million rub higher than indexes of previous period. And the volume of input of the fixed assets on results the last year made 3,9 milliards of rub, that similarly higher attained
results 2007 years more than on 1,1 milliards of rub Lining up the clear line of work on the structural co-operating with all subjects of electroenergy, in MRSK of North-west sure that successful realization of long-term investment strategy depends on all.Basic
the sourcings of the investment programs of MRSK of North-west are taken into account in a tariff on the transmission of electric power depreciation and income, paying for the technological joining and attracted credit res
sourcing of the investment program, instrument of passing ahead realization of the investment program under the guarantees of regional administration and regulator»,
realized investment projects to the amount of 1444 million rub Most essential from them: building of VL 110 kv «Voyvozh-pomozdino with PS 110 kv «Voyvozh» (Komienergo), building of PS 110 kv «Glass-house with stoppings of VL 110 kv (Vologdaenergo), reconstruction of PS 110 kv «Shuya» (Karelenergo),
reconstruction of PS 25 kv 8 (Arkhenergo), reconstruction of Oru-110 kv PS 53 (Pskovenergo). At the same time, experience, accumulated MRSK of North-west in realization of investment projects due to debt funds shows that from the side of regional authorities of obligation under
to including of facilities on service and return of the attracted credits in a tariff on a transmission in a complete size in the stipulated terms executed not always. So, in spite of the Agreement signed with the Vologda area about realization of object «building of PS 110 kv «Glass-house»
due to debt funds, with subsequent by their compensation through a tariff on a transmission 2009 years, at establishment of tariff a credit return in a sum a 150 million rub taken into account was not. «We consider that the attracted credit resources must be liquidated by tariff sources. It, with
our point of view, logically written into principles of account of interests of territories and network organization»,
organs of the North-western region. «The results of the tariff adjusting allowed 2009 years MRSK of North-west to increase the investment program with a 2,6 milliard of rub in 2008 a to 3,3 milliard of rub At the same time, the investment projects of current period will be realized only after
account of depreciation and income, taken into account by a regulator in a tariff on the transmission of electric power»,