The director of Khabarovsk Tec-3 Sergey Basha tells that the built ash disposal area 2 joins to the operating ash disposal area 1, put into an operation as early as 1985. Now he practically za¬polnen, in quick the vre¬meni upcast of ot¬khodov in him will be halted. The planned departure meeting of commission, supervising realization of one of investment projects OAO passed «DGK» – building of ash disposal area 2 Khabarovsk Tec-3 (branch «Khabarovsk generation») .direktor Khabarovsk Tec-3 Sergey Basha marked that technology
reserved cycle of the circulating water system, applied in-process and complex of buildings the station ash disposal area, is preferable not only from the economic point of view but also from ecological, because water, in-use in a technological process,
does not get in flood waters and does not contaminate will understand the rivers Amur.An ash disposal area is difficult hydrotechnical building which is equated with strategic objects. Buildings and installation works on an ash disposal area were begun as early as November, 1998 by by contract organization
LTD. «Dal’stroycentr». In 2001 on an object other contractor – OAO was attracted «Khabarovsk remontno-stroitel’naya company.Chief Oksa Alexander Strel’nikov marks Khabarovsk TEC, that in 2008 building rates were sharply accelerated. For January – October
it is the last year mastered there are more than for all period from 1997 to 2007 capital investments. The total estimate worth of project makes 694 millions 548 thousands of rub. the first quarter of 2009 was executed row of works, related to editing of electrical engineering equipment; editing
dvukhcepnoy lines 6 kv; editing of technological equipment and technological pipelines is executed in pumping defecate water; delivery of macadam was produced in a volume 26 thousands of m
defecate water with cutting in operating pipelines.Before putting into the operation of the first section of ash disposal area 2 coming to execute a large volume pa6ot directly on the dike of ash disposal area and at the pumping station.Supposed term of completion of slaves
2 Khabarovsk Tec-3 it is July, 2009. Putting into the operation of 1-oy section of ash disposal area 2 will decide the problem of collection of zoloshlakov Tec-3 on the nearest 7-8 years.