Specialists of the East enterprise of electric networks «Yantar’energo» completed works on substation 110 kv «Nesterov» on replacement of power transformer of 6300 kva more powerful 16 000 kva. With 22 for April, 25 on an object the complex assay of the mounted equipment is produced for 72 sentinel to the program, including necessary starting-up and adjustment works of transformer 110/15 kv, transformers of current 110 kv and 15 kv, equipment cells, bus
disconnector ( SHR) 110 kv, switches 110 kv and 15 kv, terminators of overstrains (ARF) 110 kv and 15 kv.
1964 years of making.According to the chief of service of substations and lines (SPL) of the East enterprise of the electric systems of Victor Malashina, in works on substation «Nesterov» the depchief of SPL Andrey Kazakov, master Evgeny Nikishin, elektroslesari, differed
Oleg Scherbakov and Alexander Skorokhodov.