Now scopes between a heating season and preparation to him are worn away. Modern technologies and equipment in many cases allow to conduct repair of pipelines kruglogodichno. It is special notedly on the example of LTD. “BASHRTS”. 12 May from teplosnabzheniya was a power-off last among the cities of republic is Neftekamsk. But already to the middle of month repair of two areas of main networks was executed by an extent 905 linear meters (6,3 % from a plan)
and fifty areas of quarterly networks by an extent 11780 linear meters (22,8 % from a plan). That to completion of heating season Bashkir teploenergetiki had time to repair fifth part of quarterly networks, reports "Bashkirenergo".to same it is possible
to say and about a caldron equipment. According to plan of repair 2009 years are planned to execute major repairs 10 steam and 13 vodogreynykh caldrons, and also permanent repair 57 steam and 188 vodogreynykh caldrons. And already to on major repairs were May, 8 executed two steam and two
hot-water boiler, permanent repair is 24 steam and 40 vodogreynykh caldrons.