On Yamale a winter season was completed. From January for May on building «Obustroystvo of senoman-aptskikh beds of Bovanenkovskogo NGKM» by subdivisions «Stroygazkonsaltinga» there was progruzheno about 45 000 piles, termostabilizaciya of soils is conducted. For pile works a screw was used and buroopusknye piles. First – mainly on linear buildings (loops of gas pipelines, gazosbornye collectors, VL 10 kv), buroopusknye – on building of ground objects (Gp-2 UKPG (1 module), aeroport, ground
hard domestic and industrial wastes, base of geophysicists, base of the boring drilling and other) Parallell with immersion of piles conducted to termostabilizacii of soils, allowing to freeze the grounds of pile foundations and provide their reliable exploitation, including in warm
time of year.Works on Yamale passed in difficult weather terms. So, in a winter season building once or twice broke in through a snow-storm, in yanvare-fevrale it was more than two put on record weeks (when a temperature stuck to below minus 45 With). With arrival of summer began
irrigation of locality, that slowed down substantially, growing which is planned to July. In this month works will be conducted on the poured out grounds, the purveyance of piles will proceed. To beginning of summer navigation (middle of July) it is planned to complete building
moorage on the river of Se-yakha, that will allow considerably to simplify delivery of loads on Bovanenkovskoe NGKM. In summer on the North sea-lane a customer (LTD. «Gazprom booty Nadym») will leave a krupnogabaritnoe equipment on building, and general contractor (LTD. «Stroygazkonsalting»)
will put metallokonstrukcii and other necessary materials.