«Engineering center ECC» in accordance with a chart carries out construction-works on power unit of Pgu-410 Mvt Sredneural’skoy GRES. Workings specifications are finished off on the mortgaged details of gas turbine and foundation of kotla-utilizatora. Presently go work on setting of armature frameworks of flags of foundations, erection of foundation of kotla-utilizatora is conducted, foundation of gas turbine and main corps. More than 100 persons work on a ground. Building will begin in the near time
to the waterside pumping station and dozhimnoy compressor station.«Engineering center ECC» got in succession on implementation of construction-works of new power unit of Pgu-410 Mvt Sredneural’skoy GRES in January, 2009. In accordance with a contract, a company provides a device
foundations of main corps of Pgu-410 Mvt, including foundations of gas turbine, steam turbine, KU and flue, waterside pumping station, vodopodgotovki for the signup of cycle (Pgu-410), KNS of industrial and domestic flows, dozhimnoy compressor station, foundations
transformers with the ways of rolling-up.A customer of project is OAO «Ogk-5», EPC-a contractor is the Spanish engineering company Iberdrola.dlya certificates. Sredneural’skaya GRES by the set power 1182 Mvt operates from 1936, provides a heat and electric power Ekaterinburg
and partly the Sverdlovsk area. The necessity of building of new power unit arose up from the obsolescence of part of operating equipment of GRES.