Editing of gas turbine of the first parogazovoy setting (PGU) of new power unit, which it is planned to bring into an action already in December of this year, began on May day TEC (Tgk-1). «Energostroyinvest-kholding» began editing of turbine of new power unit of May day TEC in Saint Petersburg. Works are executed by the specialists of general contractor on the project of reconstruction of May day TEC of OAO «Tgk-1» – OAO «A company EMK is Engineering»,
included in composition «Energostroyinvest-kholdinga».turbina is a basic element of power equipment of the station, «heart» PGU, and its editing, according to statement of specialists of kompanii-podryadchika, – the most difficult and responsible stage of building. We will remind, in May complete set
gas-turbine equipment total mass 646 tons and by volume of a more than 3000 m 3 arrived by a water-carriage in marine port of Saint Petersburg. Basic details are a generator by mass more than 107 tons, a gas turbine is 57 tons and rotor of generator – about 25 tons.In order that
to deliver parts of new turbine to the place of editing, an unique operation was conducted with the use of a number of the special mechanisms – heavy treylerov, derrick-boat in port and faucets of enhanceable carrying capacity directly on build
to the ground.According to the deputy of director general of OAO «Energostroyinvest-kholding» Aleksandra Superfina, «today one of the major stages of reconstruction of May day TEC started is editing of turbine of GTU of new power unit. Reconstruction May day
TEC is a priority project for all North-western region. Presently all works «Company Emk-inzhiniring» executes in complete accordance with the concerted chart and technical requirements». «We conducted scale preparatory work. Editing
gas turbine by power 63 Mvt, by mass more than 57 tons – very responsible and, perhaps, the most difficult part of all project on erection of new power unit, – talks member of rule OAO «Energostroyinvest-kholding», managing director of OAO «Company Emk-inzhiniring»
Mikhail Krasheninnikov. – Before the first stage of works – setting round
2007 years. The project of reconstruction foresees building of new power unit – actually, to the new station, – in composition two parogazovykh settings (PGU) by total power 360 Mvt and 270 Gkal/ch. PGU consists of two gas turbines V64.3A productions Ansaldo
Energia and steam turbine of T-50/64-7,4/0,12 productions «Power machines», two kotlov-utilizatorov productions of OAO «Podol’skiy machine-building plant».realizaciya project conducted at active support of OAO «Gazprom»by the .general’nym contractor of building subject to conditions
«turnkey» there is OAO «Company Emk-inzhiniring», included in composition «Energostroyinvest-kholdinga».