Power engineering specialists of the Western electric networks of branch of OAO «MRSK of Volga» – «Orenburgenergo» conduct the reconstruction of major energouzla region – substations 110/35/10 kv «Pleshanovskaya», revealed to the correspondent EnergyLand.info in a company. Basic part of power equipment is already mounted. Now specialists lay cables, elegazovye switches and transformers set.A reconstruction of substation is part of scale project on the increase of energonadezhnosti region. Within the framework
project the reconstruction of substation is conducted «Kalikinskaya» and building of air-track is completed 110 kilovolts «Pleshanovo-kalikino» by an extent a 47,309 km, which bound western part of the Orenburgskoy area to central and north. New line and modern
substations will allow to promote reliability of power supply of users in the western districts of Orenburzh’ya. Pryanishnikova, Orenburg