Implementation of physical indexes on all types of repair activity of basic equipment of branch OAO «MRSK of North-west» – «Pskovenergo» made more 100%, reported EnergyLand.info in press-sluzhbe of company. For 4 months 2009 years «Pskovenergo» pointed a 69,8 million rub at implementation of repairs and technical maintenance of objects of elektrosetevogo economy The overwhelming volume of works is conducted khozsposobom. As reported in the management of technical exploitation and repairs of company,
clearing of routes of VL goes along with passing of chart 35-110 and 10 kv. It direction to repair activity is instrumental in prevention of possible damages LEP and to providing of reliable power supply of users during the elemental weather phenomena.In general complication
to date «Pskovenergo» 1 400 ga of routes of air-tracks of electricity transmission produced clearing. Only in 2009 in the production separations of company it is planned to clear poryadka 3 900 ga.  From the beginning of year repair was carried out in workshop terms
13 transformers 1-2 sizes, row of TP – in Opocheckom, Ostrovskom districts and Pskove. In obedience to ratified planam-grafikam works, in production separations replacement of supports, wires and isolations, is conducted on air-tracks, muffs in cable networks, repair of production
buildings, transport and spectekhniki, devices.Within the framework of realization of the program of technical service in «Pskovenergo» rounds, examinations and removal of emergency defects, are conducted on 1,6 thousands of km of VL 110 kv, on a 960 km of VL 35 kv, on 7,1 thousands of km of VL 10 kv and on 5 thousands of km of VL 0,4 kv. Also
technical service is executed 495 things of TP 10/0,4 kv. On the whole repair program «Pskovenergo» on 2009 ratified on a lump sum 76,2 millions to the rub, program of tekhosbsluzhivaniya – in a volume 159,8 million rub