Total project worth of air-track of electricity transmission a 5,44 km makes a poryadka 50 million rub an extent Buildings and installation works on a line it is assumed to complete in April. Works on Vl-110 kv Krasavino began in December, 2008. Last year reorganization of crossings of Vl-110 was completed kv with existent Vl-6 to the kv.po words of director Velikoustyugskikh electric networks of branch of OAO «MRSK of North-west» – «Vologdaenergo» Vladimira
Migal’nikova, on the new line of electricity transmission delivery to power will be carried out in a grid with built GTEC in town Krasavino Velikoustyugskogo district.Presently on built otpayke of Vl-110 kv Krasavino editing and setting is fully completed
supports. Set 22 intermediate reinforced concrete supports and 14 metallic supports. A 3,8 kilometre of wire is mounted.