For the increase of reliability of energy supply and connecting of new users to the networks, personnel of OAO «Yantar’energo» began replacement of power transformers at once on two large substations. The specialists of the Western enterprise of the electric systems of company will replace a power transformer power 15 MVA on substation 110 kv «Gur’evskaya» by more powerful transformer 25 MVA. On substation 110 kv «Right-bank» (Tec-1) replacement of transformer will be produced
by power 40 MVA more powerful 63 Mva.Vo time of reconstruction (from May, 20 to the middle of October) reliability of energy supply in the area of action of substations will be mionectic. To beginning of works in «Yantar’energo» the protivoavariynye trainings of personnel of company are conducted, developed
programs for operative renewal of electric power of users in the cases of origin of technological violations or failures.