During throughout the year in repair of elektrosetevogo economy a company plans to inlay a 218 million rub In the first quarter of energy of company executed repair on the lines of electricity transmission of all classes of tension in a volume a 187 km A most volume of works is specialists «Arkhenergo» produced on distributive networks 6-10 kv are a 153 km Within the framework of the repair program, power engineering specialists replaced more than 620 insulators in the area of responsibility of production separations, 590 supports of lines of electricity transmission and mounted
16 km of wire. The specialists of industry cleared 6 ga of route of lines of electricity transmission from an underwood. To implementation of basic volume of works of energy will begin in summer – on the whole, during 2009 it is planned to clear 1684 ga of route. Also for the first quarter in a production
separation «Arkchangelsk electric networks» more than 40 switches of 10 (6) kv. were repaired Complex repair on the lines of electricity transmission of most volume was executed by the power engineering specialists of production separation «Arkchangelsk electric networks» are a 145 km
In general complication during a year in the area of responsibility «Arkhenergo» it is planned to repair a 130 km of VL 110 kv, 60 km of lines of electricity transmission by tension 35 kv and a 880 km of distributive networks 0,4-10 kv.