More than half of this sum – a poryadka 40 million rub is set to inlay in building of new lines of electricity transmission and substations. 15 millions will be directed on the reconstruction of one of key substations of regional center – «Western». Investprogrammoy is foresee financing of reconstruction of lines of electricity transmission 0,4 –10  kv is a 8,5 million, introduction of informacionno-izmeritel’noy CAS of commercial account rub to the amount of 3,2 million rub, acquisition of equipment almost on 2
million, an equipment of center of management networks is 6 million rub. whole, in 2009 the investment program will make a poryadka 260 million rub In the number of key projects is building of energoob’ektov for habitation, erected within the framework of national project «Accessible habitation».
In particular, it is planned to enter a 68 km of new lines of electricity transmission in work 10-0,4 kv, to extend existent substations 110 kv, and also to build transformer substations 10/0,4 kv by general power 12,69 Mvt.