From 6 to June, 16, in accordance with the program of preparation of the Far-Eastern generating company to passing of fall-winter a maximum of loadings 2009-2010 years, and in obedience to the chart of repairs of power equipment, will be fully shut-down Khabarovsk
Tec-3. At this time the Khabarovsk teplosetevaya company will conduct the planned workovers on the main thermal networks of city in the area of maintenance of Tec-3. Combination of terms of workovers is in two branches of OAO «DGK» will allow to shorten the period of absence hotter
waters for the habitants of Khabarovsk.The complete stop of Khabarovsk Tec-3 will not entail some interruptions in a power supply. Users will get electric energy from other power-stations of DGK and incorporated grid of Far East.Khabarovsk
Tec-3 already not in the first time fully stopped for the leadthrough of workovers. It is related to that part of the station equipment it is impossible to repair during work of power units. As a volume of works is planned by large, repair brigades will be
to work during all light day.During the leadthrough of repair coming contractors (OAO «KHRMK and OAO «KHPRK») and own repair personnel of the station to produce works on circulation vodovodam (replacement of scraies and turning breech-block); repair
shandor and mechanisms of the revolved nets of circulation pumps; repair of armature of circulatory vodovodov and neotklyuchaemykh areas of the heating system. Besides workovers at the station simultaneously examination of industrial safety will be produced smoke
pipes and renewal of joinings of gazokhodov to the flue.