On the site area of Leningrad Aes-2 procedure of priema-peredachi results of works passed on forming of foundation pit of turbine island of power unit 2, reported EnergyLand.info in an informative center AES. As a representative of zakazchika-zastroyschika, deputy of director of branch of OAO, marked «Business concern Energoatom» – Managements built Leningrad Aes-2 Andrey Garusov, during works on forming of foundation pit of the second block already by forces of subdivision of OAO «UAT» by contract
organizations of joint-stock COMPANY «Titan-2» about 350 thousand of m is moved
days plan to make off next meaningful volume of works, device of pilework of cooling tower 1 first power unit», – the Management representative marked.In same queue representative of General contract organization, leader of branch «Spbaep is Engineering»
Sergey Egorov marked execution by contract organizations of chart of works: «Experience, got by us on the first block, allows substantially to promote planning quality – and it is not declaration already, and the real fact».v present tense on a site area by Leningrad
Aes-2 works 920 persons of workings specialities, more than 100 units of transport and 110 special mechanisms.