OAO «Moscow incorporated elektrosetevaya company» summed up passing of fall-winter period 2008 – 2009 years. The specialists of company mark that this OZP okharakterizovalsya a low accident rate and considerable decline of traumatism. The successful passing of fall-winter a maximum of loadings serious preparation was instrumental in. Realization of the programs of remontno-ekspluatacionnogo maintenance of network economy passed with passing of chart and overfulfilment of plan. During everything 2008 years
a scale reconstruction and technical rearmament passed on energoob’ektakh. Large attention was spared to realization of the repair program. In all on repairs 4,036 milliards of rub are directed in 2008 From them 1,856 milliards of rub are inlaid in repair of distributive network
0,4 – 10 kv. A company repaired a 2 263,6 km of networks of this class of tension. MOESK annually increases facilities on a reconstruction and repairs, and the same decides the problem of increase of reliability of power supply, improvements of quality of transmission of electric power to the clients.
In addition, 0,679 milliards of rub at preparation to OZP are directed on repairs of substations by tension 35 – 220 kv and 0,246 milliards of rub – on repair of lines of electricity transmissions by tension of 35 – 220 kv. A 61 substation was repaired 35 – 220 kv and a 2 453,4 km of networks of 35 – 220 kv. As a result of conducted
works middle duration of interruptions of power supply of subscribers went down considerably – physical persons. A company aspires to the European standard on which an interruption in the power supply of users at neshtatnykh situations must not exceed two clock.
The special part of the repair program is made by the annual clearing of routes of air-tracks. On statistics, many failures on the lines of electricity transmission take place exactly from falling of trees and branches on wires. Clearing of cut-throughs reduces the level of accident rate substantially
and time of interruption of power supply in the moment of failure. In all last year on clearing of routes 0,151 milliards of rub are directed In 2008 905,5 ga (on 161 ga anymore planned) of routes of lines is cleared 6 – 10 kv and 1 383 ga of routes on lines 35 – 110 kv (according to plan are 1 362 ga) .na conference of leaders
districts of the Moscow cable networks of pe
to OZM in all branches, scale inputs of new equipment, and also reconstruction of threadbare and out-of-date equipment in distributive networks, on the lines of electricity transmission 35-110-220 kv and on feed-in centers. Company as a result of the led measures considerably
promoted reliability of power supply of users and provided the trouble-free transmission of electric energy. I consider, this success by the merit of vysokoprofessional’nogo collective of many thousands of MOESK».