In April in the branches of OAO «MRSK of North Caucasus» and OAO «Nurenergo» a repair campaign on which it is planned to send 1,01 milliards of roubles starts. As compared to indexes 2008 years a sum is megascopic on 200 million roubles. During the repair program from April for October it is assumed to repair a more than 1200 km of VL 35-110 kv, to clear from a drevesno-kustarnikovoy vegetation proseki on an area 256 ga. On these aims 83,6 million roubles must be directed.The yet greater volume of works coming
to execute in distributive networks by tension 6-10/0,4 kv. On these works 298 million roubles will be selected, that will allow to conduct regulation works on 5,9 thousands of km of air-tracks, to clear 872 ga of cut-throughs from a vegetation.The brigades of specialists will conduct works also
on replacement and repair of equipment on substations tension 35-110 kv. It is planned to replace 492 transformers and more than 3,6 thousand of switches. On repairs of substations in networks 35-110 kv and 6-10/0,4 kv 366 million roubles will be released.Most facilities on implementation of the repair program
2009 years will be mastered in branches «Stavropol’energo» (270 million rub), «Dagenergo» (184 million rub), Karachaevo-cherkesskom branch (154 million rub) and OAO «Nurenergo» (143 million rub).osnovnaya part of measures of the repair program is directed on preparation to passing of fall-winter
a maximum of loadings 2009-2010