In April in all network branches of OAO «MRSK of North Caucasus» the period of fall-winter a maximum of loadings is successfully completed. In the period of OZP 2008/2009 number of technical incidents as compared to the indexes of OZP 2007/2008 went down on 15 percents. An economic detriment in the period of OZP, caused as a result of disrepairs, went down on 27 percents on comparison information the last year. Accidents in the period of fall-winter maximum marked it was not.Within the framework of preparation to OZP 2008/2009 it was conducted 238
measures, substantially promoting reliability of network economy and transformer substations. On the repair program 743,7 million roubles were released in 2008, that allowed to execute preparation of elektrosetevykh objects to execution of the maximal loadings. Basic
by by contract organizations, executing repair of equipment OAO «MRSK of North Caucasus» to steel of OAO «SKERK»; OAO «Dagenergoremstroy»; OAO «Stavropol’specenergoremont»; OAO «Stavropol’set’energoremont».specialisty MRSK of North Caucasus already began to
to implementation of the repair program the measures of which are directed on preparation to passing of OZP 2009/2010 On these aims it is planned to send 1,01 milliards of roubles. General extent of air-tracks of electricity transmission of network branches of OAO «MRSK of North Caucasus»
makes 121,6 thousands of km; general amount of transformer substations 110-35/0,4-10 kv are 26,8 thousands by power 15550 MVA.