New substation is erected for the power supply of modern svinokompleksa joint-stock COMPANY «Kuzbasskiy pischekombinat», which must satisfy the necessities of population of cities Novokuzneck, Prokop’evsk and the Prokop’evskogo district in myasoproduktakh. For functioning of stock-raising complex it will be entered 3,25 Mvt to electric power. Work on building of substation «Dmitrievskaya» by tension 35/10 kv in the Prokop’evskom district of the Kemerovo area are in the stage of completion. Estimate cost
energoob’ekta made an about 60 million rub Power engineering specialists executed obschestroitel’nye works, two transformers set by power for 4 MVA each, mounted two cells of the opened distributive device of 35 kv. Completion of building of substation is planned
on June of this year. For completion of building remained to stretch the line of electricity transmission tension 35 kv, to produce starting-up and adjustment works and equip with modern amenities territory. Substation «Dmitrievskaya» 35/10 kv is to one of basic investment projects
branch «MRSK of Siberia» – «Kuzbassenergo – RES» in 2009.