“Repairs, conducted annually, allow to support power of Cimlyanskoy hydroelectric power PLANT at necessary level — 209 Mvt and to carry out supplying to electric power to the market in the planned mode”, — the technical director of CGES Alexander Bondarec marked. "This year "Rostov generation" will point at a repair campaign on Cimlyanskoy hydroelectric power PLANT 18 millions 75 thousands of roubles. To date from this sum a more than 4 million rub is already mastered", – revealed to the portal EnergyLand.info in OAO "YUGK Tgk-8".v end of March the capital is completed
repair of hydroelectric generator 2 by power 52,5 Mvt. Workovers proceeded 30 days. For this period model major repairs were executed, prophylactic works and control examination of workings surfaces are conducted. On it 3 millions were used up 172 thousands of rub
The primary purpose of works was providing of reliability of hydroelectric generator in a flood period the 2009 g.v flow of year is planned to make repairs all 5 hydroelectric generators. Except for it, in April the planned repair of electrical equipment will pass on Cimlyanskoy of the hydroelectric power station
I YELL 110/220 kv.