Main task of the second quarter, after successful «channel» on the opened reactor, is preparation and beginning of the stage of gidroispytaniy and circulation washing, reported EnergyLand.info in the informative center of Rostov AES. Leader of starting of power unit 2 Erik Pozdyshev, the term of readiness designated to gidroispytaniyam of the first contour – on May, 20.At guidance of operative staff on managing starting of power unit 2 there are not doubts in that terms will be observed: amount of specialists,
workings on a block, increased (only for the last month the quantity of personnel on a ground grew on 1000 persons); with supplying with materials and equipment of problems it is not; the hard is created, punctually to the minute, chart of organization of works; for the economy of time
for a few by contract organizations even dinners will deliver straight on stroyploschadku. A leader of project is a director of OAO «NIAEP» Valery Limarenko marked: «The tasks of May are certain, the participants of meeting of operative staff signed the chart of works, produced
proper order, a relay building race goes out on a finish line. Our building is an object of large importance not only for Volgodonska and Rostov area but also for all Russia. Power unit 2 Rostov AES is by a starting point in building
new atomic power units. Exactly about it on a nedavnem conference in Udomle talked Chairman of Government of Russian Federation Vladimir Vladimirovich Putin».