On Smolenskoy AES a final conference took place on a project TASIS «Support of exploitation», the specialists of the station and experts of consortium took part in which TVONS and And MEC. The participants of project, which chief of department of technological management Vladimir Pashichev heads, summed up long and tense work on perfection of methods of prevention of errors of personnel on the Smolenskoy Aes.Obschie task of project
«Support of exploitation» consisted in the improvement of safety of exploitation of the atomic station due to strengthening of understanding the personnel of SAES of factors, influencing on his job performances, and also in the leadthrough of teaching to the methods of prevention of errors and reduction
probabilities of their origin.A project can be considered successful, the put tasks are executed.All participants of meeting came to such conclusion. It was also marked on a conference, that a m of aterialy project, developed during his realization, is good basis
for further improvements in area of exploitation of the atomic stations, in particular AES with the reactor of type of Rbmk.V June, 2006 by Commission of European Communities a three-year contract was signed «Naob’ektnaya support of exploitation of Smolenskoy AES». His realization
foresees providing to the technical help on the ground of the Smolenskoy nuclear power plant within the framework of the program TASIS.«Support of exploitation» it was to one of five projects, realized within the framework of this contract on the transmission of experience and now-how.Smolenskaya AES
it is the branch of OAO «Business concern Energoatom», 100% shares of which OAO belongs «Atomenergoprom». The station is located on the south of the Smolenskoy area, in a 3 km from Desnogorska. SAES consists of three power units with uran-grafitovymi by the channel reactors of type of Rbmk-1000
on thermal neutrons. Power units are put into an operation in 1982, 1985 and 1990