One of the largest projects, which carries out OAO Bashkirenergo in the last two years», – building of sistemoobrazuyuschey substation «Back-water» 220/110/10 kv – entered into the finishing stage. On territory of substation the second power is delivered avtotransformator ATDCTN by power 125 thousands kilovoltampere and set on beforehand geared-up foundation.Unique operation on transporting from a railhead «Dema» to the built substation
«Back-water» and weighing 146 tons the specialists of Ekaterinburg organization of LTD. carried out setting on foundation of negabaritnogo load «Elektrouralspecmontazh».napomnim, that in July, 2007 in place of future substation was hammered in the first peg. In March, 2008 on major
energooob’ekt was delivered the first power transformer. Gross weight of transformer with treylerom got around a dvukhsottonnoy mark. For the choice of route it was necessary to connect travelling services. A route was developed so that on the way of lorry convoy did not appear
bridges which, alas, are unable to survive such weight. In general, delivery of transformer reminded a situation with an elephant which must it was be shown out of tableware bench, reports "Bashkirenergo". Power asm, in spite of his sizes, it is impossible it was even
slightly nakrenyat’. For this purpose it was necessary to use the German special platform Goldhofer, which automatically holds loads in horizontal position. Secondly, length of lorry convoy was order 15-16 meters, and manipulation by him, especially on the bends of road, showed
by itself the real standard of art. Naturally, did not do without surprises. Somewhere lorry convoy of probuksovyval, but by efforts of specialists of LTD. «Elektrouralspecmontazh» and OAO «Bashkirenergo» he, eventually, got to the ultimate goal.Completion all this
means operations, that building of substation entered into the second finishing phase and after completion of editing of transformer it is possible it will be to begin starting-up and adjustment works and spokoy
by works.