From June, 1, 2009 it is planned to begin replacement of hydroelectric generator (station 2) on Uglichskoy hydroelectric power PLANT. A new asm according to plan must be delivered on the Uglichskuyu hydro-electric power station to the end of present year. Almost 70 years, from December, 8, 1940, an asm serves on Uglichskoy hydroelectric power PLANT. He was started by the first at the station. His operating power – 55 Mvt. Although the last two years a hydroelectric generator worked with limitation on power to 35 Mvt. One time in two years an asm hatched on
major repairs, that testified to the high level of physical and moral wear. A project foresees substituting of asm by new with the improved technical descriptions, that will allow due to application of modern technologies, equipment
and materials to increase his reliability, safety of hydrotechnical buildings and maintainance of the water mode Uglichskoy hydroelectric power PLANT, to shorten expenses on his exploitation and repairs. A competition on replacement of hydroelectric generator was won by the Austrian company «Foyt Simens» (Voith Siemens
Hydro Power Generation GmBH), that gave status to him «pilot» project with participation the European supplier. Contract on substituting of hydroelectric generator to the station by modern, by power 65 Mvt was celled in April, 2007. In obedience to the terms of contract there is a company «Foyt Simens» carries out
dismantling of operating hydroelectric generator Uglichskoy hydroelectric power PLANT, delivery, editing and putting into the operation of new machine. A hydro-turbine will be made on the enterprises of company «Foyt Simens», gidrogenerator – in Russia, on the Novosibirsk enterprise «ELSIB». Cost 
contract works makes a more than 1,8 milliard of rub with Nds.V accordance with the ratified chart of works in a flow 2-4 quarters of 2009 it is planned to execute in full all necessary buildings and installation works on dismantling of hydroelectric generator and preparation of ground
for the reception of equipment. At the end of 2009 a supplier plans completion of making and delivery hydro-turbine and gidrogeneratornogo equipment for GA 2to the .k end 2010 years a new asm it is planned to start in an operation and maintenance phase. Increase set
powers hydroelectric power PLANT as a result of reconstruction of hydroelectric generator on 10 Mvt will result in growth of volume of making of electric energy, increase of working power and quality of system services.