Power engineering specialists of the East electric networks of branch of OAO «MRSK of Volga» - «Orenburgenergo» 110 kilovolts execute reorganization of lines «Orsk – Cleansing» and «Orsk – Ks-15». At building of highway Orenburg is Orsk there was a necessity to carry two metallic supports and set one additional on a detour area. Such decision was accepted, to observe distance at crossing and rapprochement of air
lines of electricity transmission with highways.On a line «Orsk – Ks-15» dismantling of support is already executed and two new supports are set. Production of works on a line «Orsk – Cleansing» it is planned on the last ten-day period of June.In works 12 units are involved by the special
techniques. Reorganization of lines it is planned to complete to the end of month.