On PS «Bakharevka» in Permi a new power transformer is included by power 40 MVA. A transformer will work in the mode of idling during 72 hours, with further translation him under loading, revealed to the portal EnergyLand.info in the press-centre of OAO «MRSK of Ural». We will remind that to the reconstruction on substation 110/10 kv «Bakharevka» transformers were used for 20 MVA. Replacement of one of them was conducted last year. The input of new modern transformers will soup up substation in two times.With completion of reconstruction
and modernizations of operating equipment on substation «Bakharevka» reliability of power supply of enterprises, located in the industrial area of the Sverdlovsk district, hauling substations of railway, south suburb of Permi will grow substantially. General
volume of expenses on realization of this project within the framework of the investment program «Permenergo» will make 90 million roubles.