on May, 16 after debugging on the third power unit starting operations were produced, at 14 o’clock 54 minutes power unit was plugged in a network. Presently the third power unit works on power 520 Mvt, pod’em powers conducted in obedience to regulation. Violations of limits of safe external environments are not present.Presently on Smolenskoy AES in-process the second and third power units. Their total power
1535 makes a megawatt. Power unit 1 it is under planned middle repair.