Today after completion of the planned overload of fuel, inspection and modernization of equipment, power unit of Bn-600 Beloyarskoy picked up thread work AES, reported EnergyLand.info in a center public information of AES. He was shut-down on March, 25 in accordance with a chart. In April – May on Bn-600 not only the planned regulation works on maintenance and repair of equipment but also large complex of measures are executed on preparation to the extension of calculation term of exploitation
power unit. 23 modules of parogeneratorov and 77 bolts of parovodyanoy armature are transferable, modernization of turbogenerator of Tg-6 is conducted with the increase of his power, seysmostoykost’ of pipelines is improved, control of the state of metal of equipment and other works is executed
on the program of extension of calculation term of exploitation.Atomic scientists executed all planned volume of works, to provide further reliable and safe exploitation of power unit of Bn-600 and stable making of electric power for users Sverdlovsk
areas.