Udmurtskiy branch of OAO «Tgk-5» (included in the division of Kes-kholdinga «Generation of Ural») to date executed third of all volume of workovers, planned this year on Izhevsk Tec-1, Tec-2 and Sarapul’skoy of TEC. Greater part of annual plan of preparation of equipment to the winter coming power engineering specialists to realize in the period of summer repair ground, most large works – on Tec-2. In particular at once two kapremonta: second turbine and third power caldron, which
conducted at the station presently. Power caldron 3 Tec-2 is shown out in planned kapremont from June, 15 and will pass careful preparation to the winter during three months. According to the deputy of main engineer of the Udmurtskogo branch «Tgk-5» on repair of Alexandra
Shudegova, this week power engineering specialists are engaged in preservation of kotloagregata, to protect him from corrosion during so protracted outage. For preservation the modern inhibitor of corrosion, from which on-the-spot metal the protective appears, is used
slushing tape. It allows to save reliability of equipment, prolonging the term of his service. In the turbine separation of Tec-2 kapremont of turboagregata goes at full speed 2, which began as early as April. The scale of this work is such, that for its implementation to the power engineering specialists
required even «to send on an assignment» one detail of turbine is a rotor of middle pressure weight 14 tons – on repair in the Sverdlovsk area, on Sredneural’skuyu GRES. As Alexander Shudegov told, a rotor was modernized in accordance with recommendations of zavoda-izgotovitelya
and within the next few days will be sent to Izhevsk. As soon as he will be delivered on Tec-2, he again will be set in a turbine the start of which after kapremonta is planned in the first ten-day period of August.  On the whole to preparation to the fall-winter period on Tec-2 spared traditionally
enhanceable attention. Eta «working horse» udmurtskoy energy provides almost 30% in all the volume of electric power, by a consumable republic, and two third of centralizov
works of the station.