On built Rostov AES the 5-e meeting of operative staff took place on managing starting of power unit 2. On meeting speech went about motion of starting-up and adjustment works, tasks are certain on the nearest months. In a lecture about motion of works on power unit 2 director of the Volgodonskogo branch of OAO «NIAEP» Nikolay Petrenko marked the high degree of readiness of block to beginning of gidroispytaniy and circulation washing. Taking into account labour intensiveness of this technological stage, in work
additional specialists, executing teplomontazhnye works, are included. General amount of workings on an object makes 5 675 persons, that on 1 744 more than in a previous year. Process on filling and checking for the closeness of the first contour must pressure
to begin on June, 25. Directly the tests of the first and second contours are set on July, 5. To on July, 20, when the hot rolling of reactor will begin, must be tested and ready all systems.During meeting guidance of staff before builders was put concrete
task – to on June, 25 to complete the basic editing of the technological systems, participating in the stage of gidroispytaniy and circulation washing. Also to the moment of beginning of tests assembling of reactor and compression of the first contour must be completed. Taking into account importance of forthcoming
processes on power unit 2 Rostov AES, starting of which is set on October of current year, director UKS ROAES Alexander Palamarchuk marked: «We more hardly formulated a task to by contract organizations, did it more detailed, more deep, in it reflected
every technological knot, every joint».