Cost of buildings and installation works on Boguchanskoy hydroelectric power PLANT mionectic to the amount of a 1 milliard 683,2 million roubles or on 11,7%, revealed to the portal EnergyLand.info in press-sluzhbe of OAO «Rusgidro». For optimization of investment charges on a project Boguchanskoy hydroelectric power PLANT joint commission of partners on a project OAO «Rusgidro» and OK «RUSAL» considered 14 contracts with by contract organizations. As a result of decline of size of indexation of stroitel’no-montazhnykh
works (SMR) and decline of production of daval’cheskikh materials and services cost in all contracts possibility of decline of cost is fixed on a lump sum 1683,2 million roubles or on 11,7% from the total worth of contracts.The analysis of cost of by contract works rotined
absence of overstating and, as a result, impossibility of diminishing of cost on five contracts: with LTD. «Kodinskgidrospecstroy» (drillings and blasting, cementation of stitches of concrete weir); LTD. «DSK ILAN» (erection of lateral persistent prisms of kamenno-nabrosnoy weir
(KNP), device of right-bank screen of KNP); OAO «OEK» (erection of bituminous concrete diaphragm of KNP, obschestroitel’nye works on a kamenno-nabrosnoy weir); JOINT-STOCK COMPANY "Corporation "Soyuzgidrospecstroy" (cementation of foundation of KNP and concrete weir).v nastoyaschee
time of work on all running agreements proceed. 4 a debt was May, 2009 liquidated on payment before by contract organizations for works, executed in February – March, 2009. Presently OK RUSAL again zablokiroval decisions on realization
payments to by contract organizations: representatives of Rusala on the site area of Boguchanskoy hydroelectric power PLANT renounced to sign the certificates of the executed works and provide payment of services of by contract organizations and suppliers of building materials in a volume 500 million rub for April 2009
years.Volume of capital investments in building of Boguchanskoy hydroelectric power PLANT makes 54,9 milliards of rub (taking into account VAT), actual payments on building of the hydro-electric power station on May, 18, 2009 – 25,3 milliard of rub (taking into account VAT) of .investorami in a project God
terms there are OAO «Rusgidro» and OK «RUSAL». Set power of Boguchanskoy hydroelectric power PLANT 3000 makes Mvt, the srednemnogoletnyaya making of electric power is 17,6 milliards kWh. On meeting of government of Russian FEDERATION, passing on April, 9, 2009 chaired by a prime minister
Vladimir Putin, a decision about the observance of rates and building terms was accepted with the purpose of providing of input of the first turn of Boguchanskoy hydroelectric power PLANT by power 600 Mvt in 2010, an output on complete power of all nine turbines is planned on 2012. Presently volume
executed works on building of Boguchanskoy hydroelectric power PLANT makes 75%, starting complex – 90%.