On these facilities on territory Sverdlovsk, Chelyabinskoy areas and the Permskom edge it will be repaired 8, 96 thousand of km of lines of electricity transmission 0,4-110 kv, more than 2 thousands of transformer substations and distributive points 0,4-6/10 kv, 142 substations by the class of tension
110/10 kv, 35 substations 35/10 kv. As a deputy of director general marked on technical questions – main engineer of OAO «MRSK of Ural» Yuri Lebedev at the taking place today conference of news: «Winter a maximum of loadings 2008-2009 g.g. in OAO «MRSK of Ural» characterized by a low accident rate.
In a period from November, 2008 for March  2009in the area of operating activity of OAO «MRSK of Ural» 648 technological violations are fixed, that on 9,8 %  less than as compared to OZP 2007-2008 Implementation of measures on preparation to the winter allowed to shorten nedootpusk electric power
as compared to the last year on 40%».za account of timely actions of operativno-remontnogo personnel of OAO «MRSK of Ural» on localization and removal of consequences of emergency situations middle duration of interruption of power supply of users made less than 4,5
clock. For comparison, regulated by normative certificates the size of interruption of power supply of users of the third category, which all domestic users behave to, makes 24 hours. It is needed to mark that in the large cities of the Ural region, such
as Ekaterinburg, middle duration of interruption of power supply was only 1,02 hour.In a threshold OZP 2008-2009 g.g. by the specialists of branches and subdivisions of company all necessary organizational measures were conducted. Jointly with regional organs
authorities are created Staff on providing of safety of power supply. Representatives of branches of OAO «MRSK of Ural» plugged in compositions of Staff as deputies of leaders of Staff. In all podrazd
more than 600 protivoavariynykh trainings, devoted to the features of prevention of emergency situations in the conditions of low temperatures took place. The 4 thousand employees of company took part in these measures. All personnel of OAO «MRSK of Ural» it was provided with facilities
individual and collective defence, by an overall, instruments and necessary for the production of works rigging.Additionally to the normative supply of equipment and materials branches of OAO «MRSK of Ural» were manned: 29 by a mobile movable diesel
by power-stations by general power 3,5 Mvt, by one mobile movable substation by tension 35 kv, by power 4 MVA. «Results of passing of fall-winter period 2008-2009 g.g. allow to draw conclusion that OAO «MRSK of Ural» managed with the put tasks
and provided the trouble-free and reliable power supply of users of the Ural region», – the deputy of director general marked on technical questions – main engineer of OAO «MRSK of Ural» Yuri Lebedev.