Repairs of equipment proceed on power-stations, entering in the complement of branch of OAO «DGK» – «Khabarovsk generation». Motion of repair campaign corresponds to the chart ratified before. On Khabarovsk Tec-3 from June, 6 for June, 16 an equipment with the complete stop of the station is shown out in repair, scraies and turning breech-block will replace for this time; shandor and mechanisms of the revolved nets of circulation pumps will repair; armature of vodovodov and neotklyuchaemykh
areas of the heating system.Stop of the third and fourth turns, and also permanent extended repair of turboagregata 6 are the basic considerable stages of the repair program Komsomol Tec-2. To its implementation here began at once after completion  heating season.
on the two-week stop of fourth turn of the station was May, 27 completed. Volume of works, planned for this period, on 25% exceeded the same measures the last year. Basic them them were related to verification and repair of main paroprovoda: executed diagnostics
three and replacement two gibov caldron 9, diagnostics of six bolts high pressure with replacement two from them, diagnostics and regulation of the oporno-podvesnoy system. Verification of the state of gazokhodov, repair of nourishing deaerators, and also all regulation, foreseen, is conducted
by preventive-maintenance repair of ancillaries. Works are complete in a timely manner. The third turn of the station is presently shut-down. And on June, 13 will be shown out in repair sixth turboagregat, where along with top-level, is planned
implementation of the special works.The most sums of expenses within the framework of the repair program are directed  presently on Khabarovsk Tec-1. In particular, major repairs of kotloagregata are already done 15, which was plugged in work of June, 8 – on two days before a term.
During major repairs of caldron partial replacement of pipes of screens, replacement of ceiling paroperegrevatelya, was produced above heating and gas chamber; replacement of right front block of aquatic econometer is executed, and also ten collectors of paroperegrevatelya
in connection with making of the appointed resource of work. From June, 1 on Khtec-1 under major repairs of nakh
extended repair of kotloagregata 12, where it is foreseen to replace the pipes of front and back screens from lower collectors to the mark a 9,5 m in an amount 14,5 tons.On the whole on a branch foreseen an annual plan: major repairs of 1 steam  caldron, 1 vodogreynogo,
1 turboagregata, 1 turbogenerator, 1 transformer. And also middle and current repair of equipment TEC.