In the production separations of branch of MRSK of Siberia – Altayenergo proceeds repair campaign on preparation to the forthcoming fall-winter season. In spite of difficult weather terms of present summer, power engineering specialists change supports, wires, conduct repair
substations. In Barnaul the reconstruction of line of electricity transmission proceeds 35 kv PS «Podgornaya» - PS «1-y Pod’em» - «Regional hospital». Replacement is already produced an over 3 km of odnocepnoy LEP this tension with metallic supports on 2-kh chain cable. Works will be completed
by the end of June.In the same month it is assumed to make off the reconstruction of line 10 kv «Chuya» - «Uskuch». Now replacement is here produced a 9 km of wire on samonesuschiy isolated (SIP). Only for two forthcoming summer months it is planned to produce in Altayenergo
workovers on 60 substations 35 and 110 kv, and also about 300 complete transformer substations.